煙囪(cong)爬梯制作(zuo)安裝施工進(jin)度計劃(hua)及主(zhu)要施工方法 1.1施(shi)工進(jin)度計(ji)劃 本(ben)次工(gong)程從2017年(nian)6月15日至2017年(nian)8月15日完工(gong),總工(gong)期為60天。 1.2作業流程 吊裝準備底部段(duan)安(an)(an)裝靠塔壁段(duan)安(an)(an)裝垂直段(duan)安(an)(an)裝頂(ding)部段(duan)安(an)(an)裝竣工驗(yan)收 1.3主要施工方法及(ji)技(ji)術要求 1.3.1吊(diao)裝(zhuang)準備(bei):2T卷揚機到位(wei),導(dao)向(xiang)滑輪(lun)布置好,具備(bei)起(qi)吊(diao)條(tiao)件。 1.3.2構(gou)件(jian)(jian)(jian)倒運:將(jiang)加工場(chang)制作好的構(gou)件(jian)(jian)(jian)拉運到水塔下,構(gou)件(jian)(jian)(jian)倒運時(shi),應當注意構(gou)件(jian)(jian)(jian)編號,隨(sui)用隨(sui)運,特(te)別(bie)注意垂直段Ⅱ號構(gou)件(jian)(jian)(jian)的編號及斜支(zhi)撐(cheng)的編號。 1.3.3底(di)部段安(an)(an)(an)裝:將2T卷揚機掛(gua)好底(di)部段Ⅳ號(hao)構件(jian),作(zuo)業人(ren)員站在橢圓門平臺上(shang)將連接(jie)件(jian)與水(shui)(shui)塔預埋暗榫連接(jie)。從水(shui)(shui)塔頂部設一根Φ6鋼絲繩(sheng)作(zuo)為安(an)(an)(an)全繩(sheng),在安(an)(an)(an)全繩(sheng)上(shang)配(pei)裝6m長速(su)差器,有幾個(ge)作(zuo)業人(ren)員就配(pei)幾個(ge)速(su)差器,作(zuo)業人(ren)員作(zuo)業時,安(an)(an)(an)全帶掛(gua)在速(su)差器上(shang)。 1.3.4靠塔(ta)(ta)壁(bi)(bi)段(duan)安(an)(an)裝:底部(bu)(bu)(bu)段(duan)安(an)(an)裝好后,接(jie)(jie)著安(an)(an)裝靠塔(ta)(ta)壁(bi)(bi)段(duan),先將(jiang)(jiang)構(gou)件(jian)(jian)用卷揚機起吊至(zhi)安(an)(an)裝位(wei)置(zhi),接(jie)(jie)著用螺栓連(lian)接(jie)(jie)靠塔(ta)(ta)壁(bi)(bi)段(duan)與(yu)底部(bu)(bu)(bu)段(duan)的連(lian)接(jie)(jie),全部(bu)(bu)(bu)連(lian)接(jie)(jie)好后,然后連(lian)接(jie)(jie)靠塔(ta)(ta)壁(bi)(bi)段(duan)與(yu)水塔(ta)(ta)預埋暗榫的連(lian)接(jie)(jie)件(jian)(jian)。作(zuo)業(ye)(ye)人員(yuan)作(zuo)業(ye)(ye)時站在已安(an)(an)裝好的梯子踏步(bu)上。接(jie)(jie)著安(an)(an)裝下一(yi)節(jie),直至(zhi)將(jiang)(jiang)靠塔(ta)(ta)壁(bi)(bi)段(duan)11件(jian)(jian)Ⅲ號構(gou)件(jian)(jian)安(an)(an)裝完畢,隨(sui)著安(an)(an)裝高度增加,須在構(gou)件(jian)(jian)起吊時設溜繩控(kong)制(zhi)構(gou)件(jian)(jian),以便于(yu)構(gou)件(jian)(jian)就位(wei)。 1.3.5垂(chui)直(zhi)段(duan)(duan)安(an)(an)(an)裝(zhuang):將垂(chui)直(zhi)段(duan)(duan)與(yu)(yu)塔(ta)(ta)壁(bi)(bi)暗(an)榫連接(jie)(jie)的(de)水(shui)(shui)平(ping)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)及(ji)(ji)斜(xie)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)預先安(an)(an)(an)裝(zhuang)在相應(ying)的(de)垂(chui)直(zhi)段(duan)(duan)梯(ti)(ti)子(zi)(zi)上(shang)(shang),然后起吊到(dao)安(an)(an)(an)裝(zhuang)位置,用(yong)(yong)螺(luo)栓先連接(jie)(jie)垂(chui)直(zhi)段(duan)(duan)與(yu)(yu)靠塔(ta)(ta)壁(bi)(bi)段(duan)(duan)之間的(de)連接(jie)(jie)。接(jie)(jie)著將水(shui)(shui)平(ping)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)及(ji)(ji)斜(xie)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)與(yu)(yu)相對應(ying)的(de)暗(an)榫連接(jie)(jie)。由于(yu)水(shui)(shui)平(ping)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)及(ji)(ji)斜(xie)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)隨(sui)著安(an)(an)(an)裝(zhuang)高度(du)增加而加長(chang),梯(ti)(ti)子(zi)(zi)離塔(ta)(ta)距(ju)離增大(da),人員(yuan)操(cao)作時(shi)(shi),用(yong)(yong)3塊4000mm*300mm腳(jiao)手板(ban)搭設在已安(an)(an)(an)裝(zhuang)好的(de)下(xia)部水(shui)(shui)平(ping)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)及(ji)(ji)斜(xie)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)上(shang)(shang),且用(yong)(yong)鐵(tie)(tie)絲綁(bang)(bang)扎牢(lao)固(gu),站(zhan)(zhan)在腳(jiao)手板(ban)上(shang)(shang)操(cao)作豎(shu)向斜(xie)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)與(yu)(yu)塔(ta)(ta)壁(bi)(bi)暗(an)榫的(de)連接(jie)(jie)(操(cao)作高度(du)為(wei)1400mm~1600mm),接(jie)(jie)著用(yong)(yong)措(cuo)施(shi)梯(ti)(ti)子(zi)(zi)搭設在腳(jiao)手板(ban)與(yu)(yu)塔(ta)(ta)壁(bi)(bi)上(shang)(shang),作業(ye)人員(yuan)站(zhan)(zhan)在措(cuo)施(shi)梯(ti)(ti)子(zi)(zi)上(shang)(shang)連接(jie)(jie)水(shui)(shui)平(ping)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)及(ji)(ji)水(shui)(shui)平(ping)斜(xie)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)與(yu)(yu)塔(ta)(ta)壁(bi)(bi)暗(an)榫的(de)連接(jie)(jie)。作業(ye)時(shi)(shi),安(an)(an)(an)全帶始終掛(gua)在速差器上(shang)(shang)。在腳(jiao)手板(ban)上(shang)(shang)釘橫木條,防(fang)止安(an)(an)(an)裝(zhuang)時(shi)(shi)梯(ti)(ti)子(zi)(zi)向后滑移(yi)。在距(ju)離逐漸加大(da)時(shi)(shi),增加3~4塊腳(jiao)手板(ban),腳(jiao)手板(ban)與(yu)(yu)腳(jiao)手板(ban)之間,腳(jiao)手板(ban)與(yu)(yu)水(shui)(shui)平(ping)支(zhi)(zhi)(zhi)撐(cheng)(cheng)(cheng)(cheng)(cheng)之間均用(yong)(yong)鐵(tie)(tie)絲綁(bang)(bang)扎牢(lao)固(gu)方可作業(ye)。隨(sui)著安(an)(an)(an)裝(zhuang)高度(du)增加,須在構件起吊時(shi)(shi)設麻繩控制構件,以便于(yu)構件就位。 1.3.6頂(ding)(ding)部(bu)段(duan)安裝(zhuang)(zhuang):先將(jiang)構(gou)件用(yong)(yong)卷揚機起吊至水(shui)(shui)塔(ta)(ta)頂(ding)(ding)部(bu)導向(xiang)(xiang)滑下側(ce)(ce),然(ran)后用(yong)(yong)倒(dao)鏈將(jiang)頂(ding)(ding)部(bu)段(duan)Ⅰ號構(gou)件拉(la)至水(shui)(shui)塔(ta)(ta)剛(gang)性環(huan)上(shang)(shang)部(bu)(倒(dao)鏈生根在水(shui)(shui)塔(ta)(ta)頂(ding)(ding)部(bu)預(yu)(yu)留埋(mai)(mai)(mai)件上(shang)(shang)焊接(jie)(jie)吊環(huan)),接(jie)(jie)著將(jiang)Ⅰ號構(gou)件用(yong)(yong)倒(dao)鏈放至安裝(zhuang)(zhuang)位置,用(yong)(yong)螺栓連接(jie)(jie)頂(ding)(ding)部(bu)段(duan)與垂直段(duan)的連接(jie)(jie),頂(ding)(ding)部(bu)段(duan)與靠在水(shui)(shui)塔(ta)(ta)剛(gang)性環(huan)外側(ce)(ce)的預(yu)(yu)埋(mai)(mai)(mai)件焊接(jie)(jie),焊接(jie)(jie)時焊接(jie)(jie)人員站在水(shui)(shui)塔(ta)(ta)剛(gang)性環(huan)平(ping)臺(tai)(tai)上(shang)(shang)。最后將(jiang)頂(ding)(ding)部(bu)段(duan)伸向(xiang)(xiang)平(ping)臺(tai)(tai)的兩(liang)根扶手鋼管與平(ping)臺(tai)(tai)預(yu)(yu)留埋(mai)(mai)(mai)件焊接(jie)(jie)。上(shang)(shang)塔(ta)(ta)爬梯全部(bu)安裝(zhuang)(zhuang)完。3.7外爬梯及預(yu)(yu)埋(mai)(mai)(mai)件施工 1.3.7外(wai)爬梯及預埋(mai)件(jian)施工:筒壁(bi)(bi)施工時,嚴(yan)格按(an)照設(she)(she)計(ji)(ji)圖紙預埋(mai)螺(luo)(luo)(luo)栓鐵(tie)件(jian)。預埋(mai)螺(luo)(luo)(luo)栓、暗(an)榫,鐵(tie)件(jian)均按(an)照設(she)(she)計(ji)(ji)圖紙翻樣,委托金加(jia)工隊加(jia)工。爬梯預埋(mai)件(jian)埋(mai)設(she)(she)時,根(gen)(gen)據(ju)(ju)(ju)設(she)(she)計(ji)(ji)定(ding)(ding)(ding)位(wei)(wei)(wei)尺(chi)寸(cun)(cun)在地面(mian)上(shang)放出(chu)爬梯中(zhong)心(xin)線控(kong)制樁,預埋(mai)件(jian)埋(mai)設(she)(she)位(wei)(wei)(wei)置由專職測(ce)量人員根(gen)(gen)據(ju)(ju)(ju)控(kong)制樁在筒壁(bi)(bi)鋼(gang)(gang)筋骨架上(shang)測(ce)出(chu)爬梯中(zhong)心(xin)線確(que)定(ding)(ding)(ding),上(shang)下標高根(gen)(gen)據(ju)(ju)(ju)外(wai)模(mo)所在節次標高控(kong)制。預埋(mai)螺(luo)(luo)(luo)栓固(gu)(gu)定(ding)(ding)(ding),有(you)預埋(mai)螺(luo)(luo)(luo)栓部(bu)位(wei)(wei)(wei)模(mo)板采用(yong)木模(mo)配制,根(gen)(gen)據(ju)(ju)(ju)放線定(ding)(ding)(ding)位(wei)(wei)(wei)尺(chi)寸(cun)(cun)在模(mo)板上(shang)鉆(zhan)孔(kong)打(da)眼,安裝(zhuang)固(gu)(gu)定(ding)(ding)(ding)預埋(mai)螺(luo)(luo)(luo)栓,錨(mao)(mao)固(gu)(gu)筋用(yong)扎絲(si)與(yu)筒壁(bi)(bi)鋼(gang)(gang)筋綁扎固(gu)(gu)定(ding)(ding)(ding)牢(lao)靠,同時,拆(chai)模(mo)后預埋(mai)螺(luo)(luo)(luo)栓絲(si)扣部(bu)分表面(mian)抹(mo)黃油(you),外(wai)包(bao)塑料(liao)薄膜或纏(chan)破布,防止施工過(guo)程(cheng)中(zhong)損壞(huai)絲(si)扣。鐵(tie)件(jian)與(yu)暗(an)榫固(gu)(gu)定(ding)(ding)(ding),鐵(tie)件(jian)點焊(han)在外(wai)模(mo)板表面(mian)上(shang),錨(mao)(mao)筋與(yu)筒壁(bi)(bi)鋼(gang)(gang)筋綁扎。拆(chai)模(mo)后表面(mian)用(yong)灰色油(you)漆防腐,暗(an)榫成對預埋(mai),將兩(liang)個暗(an)榫根(gen)(gen)據(ju)(ju)(ju)定(ding)(ding)(ding)位(wei)(wei)(wei)尺(chi)寸(cun)(cun)用(yong)扁鐵(tie)焊(han)接(jie)(jie)(jie)連接(jie)(jie)(jie)固(gu)(gu)定(ding)(ding)(ding)在一起,固(gu)(gu)定(ding)(ding)(ding)時,按(an)設(she)(she)計(ji)(ji)用(yong)兩(liang)根(gen)(gen)Φ10鋼(gang)(gang)筋,L=700與(yu)暗(an)榫焊(han)接(jie)(jie)(jie)做(zuo)為錨(mao)(mao)筋,用(yong)扎絲(si)與(yu)筒壁(bi)(bi)鋼(gang)(gang)筋綁扎并焊(han)接(jie)(jie)(jie)固(gu)(gu)定(ding)(ding)(ding)牢(lao)靠,暗(an)榫內(nei)抹(mo)黃油(you)并塞滿棉紗,防止砼進(jin)入暗(an)榫內(nei)。 1.3.8外爬梯加工安(an)裝(zhuang): 外爬(pa)(pa)梯根據設(she)計圖(tu)紙及(ji)筒(tong)壁曲線(xian)實(shi)際情況,對(dui)爬(pa)(pa)梯平(ping)臺(tai),爬(pa)(pa)梯各標準節,支撐等配件(jian)進行(xing)(xing)實(shi)際核對(dui)計算后,充分(fen)考慮安裝要(yao)求,翻(fan)樣,委(wei)托金(jin)加(jia)工隊加(jia)工,上(shang)塔頂(ding)爬(pa)(pa)梯所有構(gou)件(jian)中(zhong)的焊(han)(han)接采用周邊滿(man)焊(han)(han),焊(han)(han)縫不(bu)得留有殘渣,孔(kong)洞,焊(han)(han)接必(bi)須滿(man)足現行(xing)(xing)鋼結構(gou)焊(han)(han)接規(gui)(gui)程的有關規(gui)(gui)定,加(jia)工完成后,須對(dui)構(gou)件(jian)進行(xing)(xing)認(ren)真(zhen)檢查,除銹并清理干(gan)凈(jing)。對(dui)上(shang)塔爬(pa)(pa)梯及(ji)其配件(jian)進行(xing)(xing)鍍(du)鋅防(fang)腐,對(dui)平(ping)臺(tai)進行(xing)(xing)涂(tu)紅丹漆兩度,銀粉漆兩度防(fang)腐。筒(tong)壁到頂(ding)后,從下至(zhi)上(shang)逐節進行(xing)(xing)安裝。 爬(pa)(pa)梯安(an)(an)裝利用塔(ta)(ta)頂剛(gang)性(xing)環入孔(kong)處(chu)預(yu)埋(mai)(mai)一(yi)(yi)個Φ25吊環,做為(wei)導(dao)向(xiang)滑(hua)(hua)輪的固(gu)定點(dian),在塔(ta)(ta)頂部(bu)掛一(yi)(yi)2t導(dao)向(xiang)滑(hua)(hua)輪,垂(chui)直運(yun)輸用一(yi)(yi)臺1.5t卷(juan)揚(yang)機,下(xia)(xia)部(bu)2t導(dao)向(xiang)滑(hua)(hua)輪固(gu)定于人(ren)字柱支(zhi)(zhi)墩(dun)部(bu)位(wei)(人(ren)支(zhi)(zhi)柱根部(bu)),鋼絲繩用Φ11,6×37+1規格單根通長,導(dao)向(xiang)滑(hua)(hua)輪用2t導(dao)向(xiang)滑(hua)(hua)輪,卷(juan)揚(yang)機布(bu)置在30m安(an)(an)全(quan)警戒區以(yi)外,固(gu)定必(bi)須(xu)牢靠,構件吊運(yun)必(bi)須(xu)設溜(liu)繩,頂部(bu)天滑(hua)(hua)輪必(bi)須(xu)有人(ren)監護,安(an)(an)裝從下(xia)(xia)至上(shang)逐節安(an)(an)裝,先裝人(ren)孔(kong)門處(chu)第一(yi)(yi)個平(ping)(ping)臺,再往上(shang)依次(ci)裝上(shang)塔(ta)(ta)爬(pa)(pa)梯及(ji)(ji)平(ping)(ping)臺,要求連接(jie)板必(bi)須(xu)連接(jie)牢固(gu),連接(jie)螺栓(shuan)必(bi)須(xu)上(shang)緊,且保證爬(pa)(pa)梯安(an)(an)裝必(bi)須(xu)沿爬(pa)(pa)梯中(zhong)心線(xian),所有預(yu)埋(mai)(mai)件暗榫達到100%的使用率(lv)。爬(pa)(pa)梯安(an)(an)裝完成后,再安(an)(an)裝上(shang)塔(ta)(ta)扶(fu)梯及(ji)(ji)施工扶(fu)梯基礎砼部(bu)分。 1.3.9塔(ta)頂欄桿: 塔頂設內外(wai)(wai)兩圈欄桿(gan),欄桿(gan)立(li)柱采用(yong)Φ30鋼(gang)管,圍(wei)欄用(yong)40×6扁鋼(gang),剛性環挑沿(yan)及板墻施(shi)工時(shi),將欄桿(gan)立(li)柱預埋入砼內深(shen)度150㎜,欄桿(gan)鋼(gang)管,扁鋼(gang)及避雷針線應相互連(lian)(lian)接(jie)(jie)且采用(yong)焊(han)接(jie)(jie),各種材料的(de)(de)連(lian)(lian)接(jie)(jie)點處均采用(yong)焊(han)接(jie)(jie),焊(han)條(tiao)E4313,焊(han)縫高度等(deng)于被連(lian)(lian)接(jie)(jie)構(gou)件的(de)(de)最小厚度,欄桿(gan)扶(fu)手安裝頂面必須(xu)水平,嚴禁出現波浪(lang)式(shi),且保證幾何尺寸(cun)的(de)(de)準確(que)性,焊(han)接(jie)(jie)安裝完畢后,外(wai)(wai)露部分除銹并進行防腐,涂紅丹漆兩度銀粉(fen)漆兩度。 1.4作業工序的中間交(jiao)接(jie)程序 構(gou)件全部制作好,油漆涂刷完,數量及構(gou)件幾何尺寸無誤,經過驗收合格,后移交給安裝, 二、作業的質(zhi)量保證及質(zhi)量控制措(cuo)施 2.1質量保證體系(xi) 2.2質量控(kong)制措(cuo)施 2.2.1 嚴格執行質量四級(ji)檢驗、驗收制度(班組級(ji)、工地級(ji)、項目部級(ji)、監理級(ji)),上(shang)道工序(xu)驗收不合格,不得進入下道工序(xu)施工。 2.2.2安裝工程,必須設專職旁站人員進行監督(du),確保成型(xing)產品內(nei)在(zai)質量。 2.2.3明(ming)確上至隊長、下至班組成員的(de)各級崗(gang)位(wei)質量職(zhi)責,建立隊內質量獎罰制度,提高全隊人員質量意識。 2.2.4杜絕安裝工(gong)程中工(gong)藝粗(cu)糙(cao),成(cheng)品保護意識缺乏(fa)的通病(bing),嚴格做好成(cheng)品保護。 三、作業的安全(quan)技術措施及環境(jing)保護措施 3.1參加吊裝作(zuo)(zuo)業人員必須經(jing)三級安全教育,經(jing)醫療部門檢查身體狀況良好,方可上崗(gang)。作(zuo)(zuo)業前必須認真接受安全、技術(shu)交(jiao)底,并在施(shi)工中嚴格按交(jiao)底執行,遵守操作(zuo)(zuo)規程(cheng)。 3.2操作人員進入(ru)施工現場必須正(zheng)確佩帶安全帽,高(gao)處(chu)作業(ye)應系好安全帶,安全帶應掛在(zai)上方牢固可靠處(chu)(速(su)差器上),穿軟底防滑鞋。 3.3吊(diao)裝就(jiu)位人員(yuan)、電工(gong)、焊工(gong)等特(te)殊工(gong)種(zhong)作業人員(yuan)應經培訓(xun)、考試合格之后,持證上崗。 3.4施(shi)工現場應(ying)(ying)加強用火管理,嚴禁生(sheng)明火。施(shi)工現場應(ying)(ying)布設滅(mie)火器,夜(ye)間施(shi)工應(ying)(ying)有充足的照明,淋水構件吊裝嚴禁夜(ye)間施(shi)工。 3.5大風、大雨等惡劣氣(qi)候時,應(ying)停(ting)止吊裝作(zuo)業。 3.6高空操作(zuo)人(ren)員使用(yong)的工具(ju)、零件等,應放(fang)在(zai)隨(sui)身佩帶的工具(ju)袋內(nei),不得隨(sui)意向下丟擲(zhi),小型工具(ju)、連接件等裝入袋子固定于架板上。就位、脫(tuo)鉤(gou)、安裝作(zuo)業,登(deng)高人(ren)員必須(xu)將安全帶始(shi)終掛在(zai)速差器上。 3.7卷揚機應當安置在平坦堅實的地(di)方,與地(di)錨(mao)固定要(yao)(yao)牢(lao)固并(bing)要(yao)(yao)有防雨(yu)措施,卷揚機安裝時基礎要(yao)(yao)平穩牢(lao)固,周圍排水(shui)要(yao)(yao)暢通(tong),地(di)錨(mao)設(she)置要(yao)(yao)可靠,并(bing)應搭設(she)工作棚。 3.8卷揚機作(zuo)業前,應檢查(cha)卷揚機與地面的(de)固定(ding)、彈(dan)性聯軸器不得松曠。并檢查(cha)安全(quan)裝置(zhi)和鋼絲繩等(deng)、全(quan)部合格(ge)后(hou)方可使用(yong)。 3.9卷揚(yang)機與第一只導(dao)向(xiang)滑輪(lun)要對(dui)準(zhun),并垂直與卷筒中心線,導(dao)向(xiang)滑輪(lun)里檔不準(zhun)站人。 3.10鋼(gang)絲(si)繩(sheng)在卷筒上要(yao)排列整(zheng)齊不可重(zhong)疊(die)于(yu)任何一點或者高出檔板(ban),當(dang)重(zhong)疊(die)或斜(xie)繞時,應停機重(zhong)新排列,嚴(yan)禁在轉(zhuan)動中用手拉腳踩鋼(gang)絲(si)繩(sheng)。余留在卷筒上的鋼(gang)絲(si)繩(sheng)不得少(shao)于(yu)6圈。 四、作業文明施工要(yao)求(qiu)及(ji)環(huan)境保(bao)護措施 4.1 材(cai)料堆放整(zheng)齊(qi)有序,保持現場整(zheng)潔。在施工區(qu)域設施工班組標志牌,加強(qiang)文(wen)明施工管理。 4.2施工(gong)道路要(yao)及時清理,撒水濕潤,對凸凹不平(ping)處,用碎(sui)石填(tian)平(ping)。 4.3工地(di)安(an)(an)全(quan)施工制度落(luo)實到位(wei),施工安(an)(an)全(quan)措(cuo)施到位(wei),檢查施工中安(an)(an)全(quan)措(cuo)施落(luo)實到位(wei),獎罰制度到位(wei)。 4.4人(ren)員著裝整潔(jie),文(wen)明用(yong)語,嚴(yan)禁流(liu)動吸(xi)煙,嚴(yan)禁酒(jiu)后進入施(shi)工現場。 4.5現場監(jian)護(hu)人員必(bi)須監(jian)督吊裝作業(ye)按方案執行,必(bi)須嚴格履行自己崗(gang)位職責,不得違章作業(ye)。
|